Violation Detail
Standard Cited: 19100252 A02 IV General requirements.
Inspection Nr: 1313153.015
Citation: 01001
Citation Type: Serious
Abatement Date: 1
Initial Penalty: $4,205.00
Current Penalty: $2,523.00
Issuance Date: 05/30/2018
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity: 5
Report ID: 0418100
Contest Date:
Final Order: 06/08/2018
Emphasis:
Substance: 0430
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/08/2018 | $2,523.00 | Serious | ||
| Penalty | Z: Issued | 05/30/2018 | $4,205.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.252(a)(2)(iv): The individual responsible for authorizing cutting or welding operations did not designate precautions to be followed in granting authorization to proceed preferably in the form of a written permit: PCI Procoaters, Inc., Lithonia, GA - Maintenance employees were cutting and assisting during the cutting of the top of 55 gal metal containers, such as but not limited to, drums that used to contained MEK. The precautions to be followed in granting authorization to perform the cutting was not provided, on or about 4/26/18.
Translate