Violation Detail
Standard Cited: 19260451 F07 General requirements.
This violation item has been deleted.
Inspection Nr: 1310707.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 11/13/2018 2
Initial Penalty: $12,934.00
Current Penalty: $0.00
Issuance Date: 10/10/2018
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC): A
Gravity: 10
Report ID: 0625700
Contest Date: 10/31/2018
Final Order: 06/14/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 06/14/2019 | $0.00 | 11/13/2018 | Serious | |
| Penalty | C: Contested | 10/31/2018 | $12,934.00 | 11/13/2018 | Serious | |
| Penalty | Z: Issued | 10/10/2018 | $12,934.00 | 11/13/2018 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration: On or about 04/16/2018, in the EDC Unit at Westlake Chemical, the employer did not ensure that the scaffold was dismantled under the supervision and direction of a competent person qualified in dismantling a scaffold with an eccentric load applied to it by a cantilevered work platform (knee out), and by employees trained and experienced in dismantling a scaffold with an eccentric load applied to it by a cantilevered work platform (knee out).
Translate