Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
This violation item has been deleted.
Inspection Nr: 1303082.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 06/06/2018
Initial Penalty: $6,652.00
Current Penalty: $0.00
Issuance Date: 05/10/2018
Nr Instances: 1
Nr Exposed: 15
Related Event Code (REC):
Gravity: 5
Report ID: 0336000
Contest Date:
Final Order: 06/01/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/01/2018 | $0.00 | 06/06/2018 | Serious | |
| Penalty | Z: Issued | 05/10/2018 | $6,652.00 | 06/06/2018 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.147(c)(4)(ii): Procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to, 29 CFR 1910.147(c)(4)(ii)(A), (c)(4)(ii)(B), (c)(4)(ii)(C) and (c)(4)(ii)(D): a) Doren, Inc. in Wampum, PA. On or about March 20, 2018, the specific lockout procedure for the Tiger Machine did not identify all energy sources, including but not limited to the potential energy created by the base box and agitator. The procedures did not included methods to restrain the base box during servicing and maintenance. Employees perform servicing and maintenance that includes, but is not limited to, cleaning out the base box and agitator.