Violation Detail
Standard Cited: 19100217 B13 Mechanical power presses.
Inspection Nr: 1287216.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 08/07/2018 2
Initial Penalty: $4,656.00
Current Penalty: $2,793.60
Issuance Date: 06/20/2018
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity: 10
Report ID: 0522000
Contest Date:
Final Order: 07/17/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/17/2018 | $2,793.60 | 08/07/2018 | Serious | |
| Penalty | Z: Issued | 06/20/2018 | $4,656.00 | 08/07/2018 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.217(b)(13): Control reliability. When required by paragraph (c)(5) of this section, the control system shall be constructed so that a failure within the system does not prevent the normal stopping action from being applied to the press when required, but does prevent initiation of a successive stroke until the failure is corrected. The failure shall be detectable by a simple test, or indicated by the control system. This requirement does not apply to those elements of the control system which have no effect on the protection against point of operation injuries. On January 3, 2018 employees were exposed to a struck-by hazard, in that the Bliss part revolution mechanical power press, Company Number 6, did not have a control system that was constructed so that a failure within the system does not prevent normal stopping of the press when required or prevent initiation of a successive stroke.