Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1286336.015
Citation: 02001
Citation Type: Other
Abatement Date: 05/21/2018 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/25/2018
Nr Instances: 3
Nr Exposed: 6
Related Event Code (REC):
Gravity:
Report ID: 0522000
Contest Date:
Final Order: 05/15/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 05/15/2018 | $0.00 | 05/21/2018 | Other | |
| Penalty | Z: Issued | 04/25/2018 | $0.00 | 05/21/2018 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed: (a) There was no annual review of the machine specific energy control procedures.