Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1276870.015
Citation: 02001
Citation Type: Other
Abatement Date: 04/30/2018 2
Initial Penalty: $726.00
Current Penalty: $400.00
Issuance Date: 04/04/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0524200
Contest Date: 04/27/2018
Final Order: 08/13/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 08/13/2018 | $400.00 | 04/30/2018 | Other | |
| Penalty | C: Contested | 05/07/2018 | $726.00 | 04/30/2018 | Other | |
| Penalty | Z: Issued | 04/04/2018 | $726.00 | 04/30/2018 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct an annual or more frequent inspection of the energy control procedure to ensure that the procedure and the requirements of this standard are being followed: a) A periodic inspection of the energy control procedure(s) was not performed at least annually to identify potential deficiencies and to ensure skill proficiency was maintained while utilizing the procedure(s).