Violation Detail
Standard Cited: 19100212 A03 II General requirements for all machines.
Inspection Nr: 1275658.015
Citation: 01001
Citation Type: Serious
Abatement Date: 06/15/2018 2
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 03/29/2018
Nr Instances: 2
Nr Exposed: 4
Related Event Code (REC): R
Gravity: 10
Report ID: 0317700
Contest Date:
Final Order: 04/25/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | P: Petition to Mod Abatement | $12,934.00 | 06/15/2018 | Serious | ||
| Penalty | I: Informal Settlement | 04/25/2018 | $12,934.00 | 05/15/2018 | Serious | |
| Penalty | Z: Issued | 03/29/2018 | $12,934.00 | 05/15/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.212(a)(3)(ii): Point(s) of operation of machinery were not guarded to prevent employee(s) from having any part of their body in the danger zone(s) during operating cycle(s): a) Production Area: The ISB Merlin 3000 light curtain system on Cincinnati hydraulic press brake (135-CB-8 #46874) was installed in a way that allowed the operator to reach into the point of operation during the operating cycle, on or about November 7, 2017. b) Production Area: The Link Lite Black Max light curtain system on Cincinnati press brake PB-01 (175AF-10 #49569) was fitted with 6 blanking panels which created a gap in the protection zone that was large enough for the operator to reach into the point of operation during the operating cycle, on or about January 4, 2018. ABATEMENT DOCUMENTATION AND CERTIFICATION REQUIRED
Translate