Standard Cited: 19100147 D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1275487.015
Citation: 01001
Citation Type: Serious
Abatement Date: 02/14/2018 2
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 02/02/2018
Nr Instances: 1
Nr Exposed: 34
Related Event Code (REC): R
Gravity: 10
Report ID: 0524200
Contest Date:
Final Order: 03/02/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 02/02/2018 | $12,934.00 | 02/14/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6): (a) High Bay - On or about November 4, 2017, employees engaged in threading plastic sheeting through the extruder lines were exposed to machine hazards from moving parts and in-running nip points while threading the material with the line(s) operating. Employees were threading the plastic sheeting through the various sections of Extruder Line #2 when an employee's hand was pulled into the in-running nip point of the multi-roll mill section of the extruder line causing a severe injury to the employee's hand. The employer failed to implement energy control application steps as the machine was not shut down or turned off to perform the servicing work [per the 1910.147(d)(2) requirements]. As a result, the remaining applicable energy control elements, involving machine isolation [(d)(3)], LOTO device application [(d)(4)], dissipation of residual energy [(d)(5)(i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.