Violation Detail
Standard Cited: 19100333 B02 II A Selection and use of work practices
Inspection Nr: 1269843.015
Citation: 01001
Citation Type: Serious
Abatement Date: 12/19/2017 2
Initial Penalty: $12,675.00
Current Penalty: $8,872.50
Issuance Date: 12/07/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0418300
Contest Date:
Final Order: 01/03/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/03/2018 | $8,872.50 | 12/19/2017 | Serious | |
| Penalty | Z: Issued | 12/07/2017 | $12,675.00 | 12/19/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.333(b)(2)(ii)(A): Safe procedures for deenergizing circuits and equipment were not determined before circuits and equipment were denergized: a) On or about 10/05/2017 - Cast house basement, unit #4 converter, employees conducting electrical maintenance on a converter did not have procedures in place to ensure that all components in the converter cabinet were deenegerized prior to performing maintenance.