Violation Detail
Standard Cited: 19100333 B02 II B Selection and use of work practices
Inspection Nr: 1267519.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $8,149.00
Current Penalty: $6,112.00
Issuance Date: 11/27/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 5
Report ID: 0317500
Contest Date:
Final Order: 12/15/2017
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/15/2017 | $6,112.00 | Serious | ||
| Penalty | Z: Issued | 11/27/2017 | $8,149.00 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.333(b)(2)(ii)(B): The circuits and equipment to be worked on were not disconnected from all electric energy sources: a) Building 47, 30 Curry Avenue, Canonsburg, PA 15317: On or about September 28, 2017, a potential transformer that was contained within a substation style transformer (serial number R-08718-1) was not disconnected from all electric energy sources. A work bench used to provide power a load tap changer (LTC) motor also provided power to the potential transformer. The potential transformer converted the power to approximately 2000 volts on the high voltage side. Employees performing ratio and resistance testing were exposed to the hazards of electric shock and electrocution while working in close proximity to the potential transformer bushings.