Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1263375.015
Citation: 01001A
Citation Type: Other
Abatement Date: 01/29/2018 2
Initial Penalty: $5,387.00
Current Penalty: $2,693.50
Issuance Date: 01/02/2018
Nr Instances: 1
Nr Exposed: 11
Related Event Code (REC): R
Gravity:
Report ID: 0729300
Contest Date:
Final Order: 01/09/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/09/2018 | $2,693.50 | 01/29/2018 | Other | |
| Penalty | Z: Issued | 01/02/2018 | $5,387.00 | 01/29/2018 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: The employer did not provide to the employee(s) energy control procedures which outlined the step for shutting down, isolating, and securing the Promatic Bipak Cartoner (Serial No. 7303232; Year of Construction: 2004; V 230, Hz 60, kW 9; Phase 3/T) to control hazardous energy.