Violation Detail
Standard Cited: 19100146 C06 Permit-required confined spaces
Inspection Nr: 1259737.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $12,934.00
Current Penalty: $10,993.90
Issuance Date: 02/27/2018
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC): A
Gravity: 10
Report ID: 0317500
Contest Date: 03/19/2018
Final Order: 09/28/2018
Emphasis:
Substance: 1480
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 09/28/2018 | $10,993.90 | Serious | ||
Penalty | C: Contested | 04/20/2018 | $12,934.00 | Serious | ||
Penalty | Z: Issued | 02/27/2018 | $12,934.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.146(c)(6): When there were changes in the use or configuration of a non-permit confined space that could increase the hazards to entrants, the employer did not reevaluate that space and, when necessary, reclassify it as a permit-required confined space: a) In the North Division Vault of the North LDS Pond, on or about August 29, 2017 - The employer failed to reevaluate and reclassify the vault as a permit-required confined space before mechanical contractors began to open the 24-inch LDS pipe line which introduced a water engulfment hazard, hydrogen sulfide atmospheric hazard and hazards associated with oxygen fuel gas torch use into the space.