Violation Detail
Standard Cited: 19260416 A01 General requirements.
Inspection Nr: 1240990.015
Citation: 01005
Citation Type: Serious
Abatement Date: 12/20/2017 2
Initial Penalty: $5,070.00
Current Penalty: $3,000.00
Issuance Date: 09/29/2017
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 10/23/2017
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/23/2017 | $3,000.00 | 12/20/2017 | Serious | |
| Penalty | Z: Issued | 09/29/2017 | $5,070.00 | 11/20/2017 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1926.416(a)(1): Employees were permitted to work in proximity to electric power circuits and were not protected against electric shock by de-energizing and grounding the circuits or effectively guarding the circuits by insulation or other means: a) One Avenue L, Newark, NJ 07105 - MCC 35N Employees did not effectively guard energized circuits while making power connection from 480 volt main switch gear to 1200 amp feeder/disconnect switch. On 6/3/2017, an employee received second degree burns when an arc flash occurred. Violation occurred on or about 6/3/2017