Violation Detail
Standard Cited: 19260502 D06 I Fall protection systems criteria and practices.
Inspection Nr: 1219589.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $3,079.00
Current Penalty: $1,750.00
Issuance Date: 06/07/2017
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0523400
Contest Date:
Final Order: 07/18/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/18/2017 | $1,750.00 | Serious | ||
Penalty | Z: Issued | 06/07/2017 | $3,079.00 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.502(d)(6)(i): Snap hooks were connected directly to webbing, rope or wire rope: (a) The employer did not ensure that employees had their snap hooks connected to the designated and required anchor points on the work platform frame.