Violation Detail
Standard Cited: 19100269 N02 Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1213601.015
Citation: 01001
Citation Type: Serious
Abatement Date: 07/12/2017 2
Initial Penalty: $11,408.00
Current Penalty: $7,985.00
Issuance Date: 06/09/2017
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0626300
Contest Date:
Final Order: 06/29/2017
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/29/2017 | $7,985.00 | 07/12/2017 | Serious | |
| Penalty | Z: Issued | 06/09/2017 | $11,408.00 | 07/06/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(n)(2): For any employee to work transmission and distribution lines or equipment as deenergized, the employer did not ensure that the lines or equipment were deenergized under the provisions of paragraph (m) of this section and did not ensure proper grounding of the lines or equipment as specified in paragraphs (n)(3) through (n)(8) of this section: a) This violation occurred on or about February 23, 2017, when employees working on ungrounded power lines were exposed to electrical hazards.