Violation Detail
Standard Cited: 19261203 A
Inspection Nr: 1155266.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 11/22/2016 5
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/09/2016
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0626300
Contest Date:
Final Order: 11/29/2016
Emphasis:
Substance: 8870
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/29/2016 | $0.00 | 11/22/2016 | Serious | |
| Penalty | Z: Issued | 11/09/2016 | $0.00 | 11/22/2016 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.1203(a): Before it began work at a worksite, the employer did not ensure that a competent person identified all confined spaces in which one or more of the employees it directed may have worked, and did not identify each space that was a permit space, through consideration and evaluation of the elements of that space, including testing as necessary: (a) On or about June 14, 2016 at the Ter-Jan Carpet Cleaning building where the employer did not evaluate the attic crawl space, a confined space, for electrical hazards that could trigger permit required confined space requirements.