Violation Detail
Standard Cited: 19260850 A Preparatory operations.
Inspection Nr: 1117839.015
Citation: 01003
Citation Type: Serious
Abatement Date: 08/19/2016 2
Initial Penalty: $6,300.00
Current Penalty: $5,670.00
Issuance Date: 07/07/2016
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0420600
Contest Date:
Final Order: 07/21/2016
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/21/2016 | $5,670.00 | 08/19/2016 | Serious | |
| Penalty | Z: Issued | 07/07/2016 | $6,300.00 | 08/02/2016 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.850(a): An engineering survey was not performed by a competent person to determine the conditions of the framing floors and walls and the possibility of unplanned collapse of any portion of the structure prior to permitting employees to start demolition operations. At the Preliminary Treatment Structure located at the 3510 East Laurel Road, Venice, FL 34275. (a) Employees were cutting and chipping a concrete slab when an engineering survey had not been performed. One of the employees was cutting underneath a 5,000 lb. concrete slab when the slab collapsed, fatally injuring the employee, on or about 01/14/2016.