Violation Detail
Standard Cited: 19100269 D06 IV Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1108575.015
Citation: 01002B
Citation Type: Other
Abatement Date: 04/15/2016 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/01/2016
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity:
Report ID: 0625700
Contest Date:
Final Order: 04/12/2016
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/12/2016 | $0.00 | 04/15/2016 | Other | |
| Penalty | Z: Issued | 04/01/2016 | $0.00 | 04/15/2016 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.269(d)(6)(iv): Lockout or tagout devices were not affixed to each energy isolating device by authorized employees. Sabine Pass LNG Plant - Load Bank Area: On or about November 9, 2015, the employer did not ensure that employees performing maintenance, inspection and testing affixed lockout/tagout devices to each energy isolating device.
Translate