Violation Detail
Standard Cited: 19100269 D02 IV B Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1108575.015
Citation: 01002A
Citation Type: Other
Abatement Date: 04/15/2016 2
Initial Penalty: $7,000.00
Current Penalty: $5,600.00
Issuance Date: 04/01/2016
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity:
Report ID: 0625700
Contest Date:
Final Order: 04/12/2016
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/12/2016 | $5,600.00 | 04/15/2016 | Other | |
| Penalty | Z: Issued | 04/01/2016 | $7,000.00 | 04/15/2016 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.269(d)(2)(iv)(B): The energy control procedures did not clearly and specifically outline the scope, purpose, responsibility, authorization, rules, and techniques to be utilized for the control of hazardous energy, including, but not limited to the specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: On or about November 9, 2015, the employer did not develop specific procedural steps for shutting down, isolating, blocking and securing equipment for the Avtron K922A and K922B outdoor resistive load banks to control hazardous energy.