Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 110793.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $4,620.00
Current Penalty: $4,620.00
Issuance Date: 04/20/2012
Nr Instances: 2
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 10
Report ID: 0521700
Contest Date:
Final Order: 05/30/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 04/20/2012 | $4,620.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows: a. On or about December 29, 2011, at the above addressed jobsite, an employee was exposed to a fall while performing plastering operations from a tubular welded frame scaffold, approximately twenty-one (21) feet above the ground, that did not have the working level fully planked.