Violation Detail
Standard Cited: 19100333 B02 Selection and use of work practices
Inspection Nr: 1080903.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 01/25/2016 2
Initial Penalty: $7,000.00
Current Penalty: $0.00
Issuance Date: 01/19/2016
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0524530
Contest Date:
Final Order: 01/28/2016
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/28/2016 | $0.00 | 01/25/2016 | Serious | |
| Penalty | Z: Issued | 01/19/2016 | $7,000.00 | 01/25/2016 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.333(b)(2): While the employee was exposed to contact with live parts of fixed electrical equipment or circuits which have been de-energized, the circuits energizing the parts were not locked out or tagged out or both in accordance with the requirement in this paragraph. At the Shawnee Community College gymnasium in Ullin, Illinois, while replacing light fixtures employees were exposed to 286 volt live and de-energized parts and the circuits energizing the parts were were not were not locked out or tagged out or both.