Violation Detail
Standard Cited: 19100036 B01 Design and construction requirements for exit routes.
Inspection Nr: 1042471.015
Citation: 01004A
Citation Type: Serious
Abatement Date: 02/01/2017 2
Initial Penalty: $2,975.00
Current Penalty: $1,700.00
Issuance Date: 07/01/2015
Nr Instances: 2
Nr Exposed: 4
Related Event Code (REC):
Gravity: 5
Report ID: 0627700
Contest Date:
Final Order: 08/13/2015
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/13/2015 | $1,700.00 | 02/01/2017 | Serious | |
| Penalty | Z: Issued | 07/01/2015 | $2,975.00 | 08/14/2015 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.36(b)(1): At least two exits routes were not available to permit prompt evacuation of employees during an emergency: a. On or about February 20, 2015, tank battery, two exit routes were not provided for the crude oil storage tank platform where employees worked with liquids containing crude oil (flammable liquid). b. On or about February 20, 2015, tank battery, two exit routes were not provided for the saltwater storage tank platform where employees worked with liquids containing crude oil (flammable liquid).
Translate