Violation Detail
Standard Cited: 19260251 E08 III Rigging equipment for material handling.
Inspection Nr: 1014679.015
Citation: 01002
Citation Type: Serious
Abatement Date: 01/14/2015 2
Initial Penalty: $2,800.00
Current Penalty: $1,960.00
Issuance Date: 01/06/2015
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity: 5
Report ID: 0111100
Contest Date:
Final Order: 01/16/2015
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/16/2015 | $1,960.00 | 01/14/2015 | Serious | |
| Penalty | Z: Issued | 01/06/2015 | $2,800.00 | 01/14/2015 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.251(e)(8)(iii): Synthetic web slings with snags, punctures, tears or cuts were not immediately removed from service: City Park - The DD synthetic web sling with multiple cuts was not immediately removed from service.