Violation Detail
Standard Cited: 19260950 D01 IV General.
This violation item has been deleted.
Inspection Nr: 1004567.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 06/11/2015
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 04/24/2015
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0317700
Contest Date: 05/18/2015
Final Order: 06/20/2016
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 06/20/2016 | $0.00 | 06/11/2015 | Serious | |
| Penalty | C: Contested | 05/21/2015 | $0.00 | 06/11/2015 | Serious | |
| Penalty | Z: Issued | 04/24/2015 | $0.00 | 06/11/2015 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.961(c)(7): The employer did not ensure the installation of protective grounds as required by � 1926.962: a) 6533 Interchange Rd., Lehighton, PA: On or about October 27, 2014, employees were in the process of installing lightning arrestors on a 69KV power line in close proximity to energized 500KV and 69KV power lines and protective grounds were not installed, resulting in the electrocution of an employee. Abatement Certification and Documentation Required.