Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1784797.015
Citation: 02001
Citation Type: Other
Abatement Status: Corrected During Inspection
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/06/2025
Nr Instances: 3
Nr Exposed: 2
Abatement Date:
Gravity:
Report ID: 0418600
Contest Date:
Final Order: 02/05/2025
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 02/05/2025 | $0.00 | Other | ||
| Penalty | Z: Issued | 01/06/2025 | $0.00 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii): Procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to, 29 CFR 1910.147(c)(4)(ii)(A), (c)(4)(ii)(B), (c)(4)(ii)(C) and (c)(4)(ii)(D): a) Production Area - On or about October 29, 2024, and at times prior to, the energy control procedures for the Number One Rip Saw and the Planer did not include the shutdown steps prior to isolating, the steps of placement, removal and transfer of lockout devices, and the steps for verification of the elimination of hazardous energies.
Translate