Violation Detail
Standard Cited: 19100219 F03 Mechanical power-transmission apparatus.
Inspection Nr: 951916.015
Citation: 01005
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $2,800.00
Current Penalty: $1,820.00
Issuance Date: 06/09/2014
Nr Instances: 3
Nr Exposed: 6
Abatement Date: 06/30/2014
Gravity: 10
Report ID: 0523900
Contest Date:
Final Order: 07/03/2014
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/03/2014 | $1,820.00 | 06/30/2014 | Serious | |
Penalty | Z: Issued | 06/09/2014 | $2,800.00 | 06/30/2014 | Serious |
Text For Citation: 01 Item/Group: 005 Hazard:
29 CFR 1910.219(f)(3): Sprocket wheels and chains which were seven (7) feet or less above floors or platforms were not enclosed: (a) Buchman Lumber Company, throughout the facility; Chain and sprocket drives were not effectively guarded, such as, but not limited to: (1) Sawmill, Edger Operator station; The chain and sprocket drive on the conveyer system at the lumber transfer point was not guarded, and (2) Old Planer Building, Planner feed conveyor; The chain and sprocket drives to the planer feed conveyor was not fully enclosed, and (3) Old Planer Building, Planner discharge conveyor; The chain and sprocket drives to the planer discharge conveyor was not fully enclosed.