Violation Detail
Standard Cited: 19180085 K02 Containerized cargo operations.
Inspection Nr: 1242274.015
Citation: 01003
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $7,696.00
Current Penalty: $5,002.40
Issuance Date: 12/11/2017
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 01/08/2018
Gravity:
Report ID: 0418400
Contest Date: 12/21/2017
Final Order: 12/03/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 12/03/2018 | $5,002.40 | 01/08/2018 | Other | |
| Penalty | C: Contested | 12/28/2017 | $7,696.00 | 01/08/2018 | Serious | |
| Penalty | Z: Issued | 12/11/2017 | $7,696.00 | 01/08/2018 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1918.85(k)(2): When fall protection systems required by 29 CFR 1918.85(j) were employed, fall protection systems that were subjected to impact loading were used before being inspected and determined by a designated person to be undamaged and suitable for use. A) Shore side of vessel Spirit of Tokyo, on or about June 22, 2017, the employer had not ensured that each fall protection system subject to impact loading be withdrawn from service and not used again until inspection and determined by a designated person to be undamaged and suitable for use.