Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 912836.015
Citation: 01001
Citation Type: Serious
Abatement Date: 07/18/2013 2
Initial Penalty: $2,000.00
Current Penalty: $1,000.00
Issuance Date: 07/12/2013
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0316100
Contest Date:
Final Order: 07/26/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/26/2013 | $1,000.00 | 07/18/2013 | Serious | |
Penalty | Z: Issued | 07/12/2013 | $2,000.00 | 07/18/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): a) West Side of the Building - A foreman and a laborer were observed on a tubular welded frame scaffold which was not fully decked exposing them to a 26 foot fall hazard, on or about 06/20/13. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.