Inspection Detail
Inspection: 311317614 - Magro Air Conditioning & Heating
Inspection Information - Office: Austin Area Office
Site Address:
Magro Air Conditioning & Heating
Port San Antonio Bldg 375 Boeing Aerospace Support
San Antonio, TX 78226
Mailing Address:
3002 Meadow Rain St, San Antonio, TX 78251
Union Status: NonUnion
SIC:1711
NAICS: 238220/ Plumbing, Heating, and Air-Conditioning Contractors
Inspection Type: Accident
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 11/19/2008
Emphasis:
Case Closed: 02/12/2009
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 100604909 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 1 | ||||
| Current Violations | ||||||
| Initial Penalty | $2,000 | $0 | $0 | $0 | $0 | $2,000 |
| Current Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260021 B02 | 01/20/2009 | 01/26/2009 | $2,000 | $2,000 | $0 | I - Informal Settlement | Citation has been deleted. |
Investigation Summary
On September 15, 2008, an electrician and two coworkers were at a site to service overhead heaters. The electrician entered a fenced in area that contained high-voltage and exposed energized circuits. While in this area a 13.8-kV disconnect shorted, exposing the electrician to an arc blast. The employee died after spending two months in the hospital, recuperating from his injuries.
Keywords: MAINTENANCE, HEATER, ELECTRICIAN, ELEC CIRC PART--MISC, ELECTRIC SHOCK
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 311317614 | Fatality | Electric Shock | Occupation not reported |