Case Study 7: Overhead Crane Servicing and Maintenance

Correct.  The employer is not required to develop two separate energy control programs.

The employer could develop and implement a single written energy control program provided that this program addressed the applicable requirements of both 29 CFR 1910.147 and 29 CFR 1910.333.