| Standard Number: | 1926.550 |
July 20, 1990 Donald W. Johnson Safety Director McLean Construction Company 6700 Curtis Court Glen Burnie, Maryland 21061-6480 Dear Mr. Johnson, This is in response to your request for a temporary variance and correspondence with Jim Concannon, Office of Variance Determination to delay the effective date of the anti-two-blocking standard (1926.550(g)). As you know the final rule regarding crane or derrick suspended personnel platforms was published August 2, 1988, with an original effective date of October 3, 1988. Unfortunately, anti-two-blocking devices were not as readily available from manufacturers as had been anticipated, and it was not the Occupational Safety and Health Administration's (OSHA) intent to enforce a standard that could not be reasonably complied with. Therefore, on June 26, 1989, OSHA issued interim enforcement guidance to the field and delayed the effective compliance date to December 31, 1989, to allow employers additional time for delivery and installation of anti-two blocking devices. The preamble to the final rule explains that the record supports OSHA's determination that hoisting a suspended personnel platform with a crane or derrick constitutes a significant hazard to hoisted employees and that it is prohibited unless there is no feasible safe alternative. The preamble further states that cranes and derricks are not manufactured for use as personnel hoists, thus supporting the claim that some cranes cannot be retrofitted with two-block-devices. As indicated by the Summary of the Regulatory impact Analysis (53 FR 29139), OSHA is aware that "some cranes, especially older mechanical ones, would require considerable modification in order to comply with the standard". The Agency has anticipated that some of those older cranes would be to difficult or expensive to retrofit. Recognizing this fact and the general prohibition against hoisting personnel with cranes or derricks, it would [not] be appropriate for OSHA to make special allowances or approve the use of any equipment or procedures that cannot comply with the current requirements of the standard. It is the responsibility of the employer, who determines that the use of a personnel platform is the only safe method available, to provide equipment that complies with all elements of the regulations. If a particular lattice boom crane cannot be adapted to use anti-two-blocking devices, it shall not be used to hoist personnel. Sincerely, Gerald P. Reidy, Director Office of Construction and Maritime Compliance Assistance [Corrected 09/20/2006] |
|
|

Newsletter
RSS Feeds
Print This Page
Text Size