December 22, 1987
Mr. D. Victor
Saleeby Scaffold Industry Association
14039 Sherman Way
Van Nuys, California 91405
Dear Mr. Saleeby:
This is in response to your letter of November 27, requesting a
clarification of the 29 CFR [1926.452(j)(7)] requirement for pump jack
scaffolds.
29 CFR [1926.452(j)(7)] requires that "if two by fours are spliced to make up
the pole, the splicer shall be so constructed as to develop the full strength
of the members." (Correction 10/02/98) ["when two by
fours are spliced to make a pole, mending plates shall be installed at all splices to develop
the full strength of the member."] It is the intent of the above
mentioned requirement to allow the use of spliced poles for pump jacks in lieu of two continuous
length poles provided the splices are constructed in a manner that develops
the full strength of the spliced member. The spliced pole is required to
provide the equivalent strength of two continuous length two by fours poles
for pump jack scaffolds.
If we can be of further assistance, please let us know.
Sincerely,
Thomas J. Shepich, Director
Directorate of Field Programs
|