August 20, 1982
MEMORANDUM FOR: JAMES W. LAKE
REGIONAL ADMINISTRATOR
THRU: JOHN B. MILES, JR.
DIRECTOR, OFFICE OF FIELD COORDINATION
FROM: PATRICK R. TYSON
DIRECTOR, FEDERAL COMPLIANCE
AND STATE PROGRAMS
REFERENCE: Your Memorandum for the Office of Construction and
Civil Engineering Safety Standards Dated July 21,
1982.
SUBJECT: 29 CFR 1926.552(c)(3) - Personnel Hoists
The second sentence of 29 CFR 1926.552(c)(3) was included to cover
situations in which the tower is erected prior to construction of the
structure or for installations in which the tower cannot be anchored by
tie-ins to the structure at 25 feet intervals. Guys are required at what
ever intervals that are necessary to ensure stability of the tower, thru
providing employers with some flexibility for variable installation
conditions.
|