29 CFR 1910.119(j)(5): The employer does not correct deficiencies in equipment that are outside acceptable limits (as defined by process information in 29 CFR 1910.119(d) before further use or in a safe and timely manner: a.BP-Husky Refining, LLC - Oregon, Ohio: The employer does not ensure PSV-124, located in the Alky Unit, is properly designed. PSV-124 provides protection to the Isobutane Product Coalescer by relieving hydrocarbons to the flare and was determined to be undersized and does not have an adequate relieving rate during relief scenarios. Pursuant to 29 CFR 1903.19, within ten (10) calendar days of the abatement date, the employer must submit documentation that it has abated the hazard. In addition, under 29 CFR 1903.19(e), the employer must submit an abatement plan describing the actions it is taking to ensure that it is in compliance with the standards for all pressure vessels in the refinery, including documentation that each pressure vessel is evaluated and protected by pressure-relieving device(s) that is appropriate for the vessel in accordance with recognized and generally accepted good engineering practices, such as the ASME Boiler and Pressure Vessel Code. The abatement plan shall establish dates during the next three months when the evaluations and installation of adequate overpressure protection shall be completed. Once the plan has been fully implemented, the employer must submit certification of its full compliance with the standard.
|