Case Study 7: Overhead Crane Servicing and Maintenance
Incorrect.
The employer is not required to develop two separate
energy control programs.
The employer could develop and implement a single written
energy control program provided that this program addressed the applicable
requirements of both
29 CFR 1910.147 and
29 CFR 1910.333.
|