Correct.
The energy control procedure provisions require the
documentation of procedures that clearly and specifically outline elements
described in
29 CFR 1910.147(c)(4)(ii). Because of the need to follow specific steps to
successfully lockout a machine or piece of equipment as illustrated by this
incident, a documented procedure is necessary for most energy control
situations.
|