    TEXT VERSION OF TITLE SLIDE:

    Title: Developing a Tree Harvesting Plan
    Type: Text and Image Slide
    Content:

    A tree harvesting plan should be developed to address the hazards associated with a specific logging site.

    Hazards to consider in developing the plan include:

    • Overhead hazards including electric lines (29 CFR 1910.133(c)(3))

    • Danger Trees including Stubs, Spring Poles, Wind Blowns, and Widow Makers

    • General Environmental and Working Conditions

    • Adequate separation of operations while maintaining visual or audible contact

    [Image of two workers chopping trees with fallen trees in between them and text: Fallers working too close]